SAP CS 8.0 - question to parallel tasks in one job chain

$
0
0

Dear all,

 

I have a question about job chains in SAP CPS/Redwood

 

We have a job chain like this:

 

Job 1

     Job 1.1

               Job 1.1.1

               Job 1.1.2

     Job 1.2

                Job 1.2.1

...

 

The Jobs 1.1.1 and 1.1.2 should start  when the Job 1.1 is compled and don't have to wait until Job 1.2 is complete.

 

How could I release it in Redwood in one job chain? Should I use a precondition in the job definition of 1.1 and 1.2?


Thank you for your help.


Best regards,


Hans